CLEANCRETE FLOOR CHURCH AUF DER EGG
From October 2021 to April 2022 a Cleancrete floor of 500 m2 was built in the basement of the Kirche Auf der Egg in Zürich Wollishofen. The project was planned by Gianluca De Pedrini and executed by the construction company Lehmag. The Cleancrete was produced by Kibag in their concrete plant in Schlieren and transported to the construction site by conventional concrete mixer.
- Location:
- Switzerland
- Date:
- 2022



The fresh Cleancrete was pumped over 70m into the basement and applied directly on the previous floor, where it was levelled and left to dry.